Costain news

Solving The Energy Crisis

11 March 2010

As the UK's North Sea gas reserves dwindle and the country increasingly relies on supplies from overseas, the need for reserves to cope with peaks in demand and other contingencies becomes ever greater.

To improve this situation Costain is helping to create huge gas storage facilities deep under the Cheshire countryside.

Cheshire has one of the UK's main rock salt deposits and two projects involve pumping water down wellheads to the salt beds around 600 metres below the surface. The water dissolves the salt and the resulting brine is then extracted, creating vast underground caverns.

The first of these, the Stublach Gas Storage Project, will create 28 caverns capable of holding 400 million m³ of gas by 2018.

It will accept natural gas from the UK's national transmission system, storing it until needed to cope with spikes in demand.

Costain's involvement in the £400 million project initially involved front-end engineering design (FEED) of the brine and water facilities for INEOS, which subsequently 'sold' the project to Storengy, a subsidiary of the giant French-based GDF SUEZ energy company.

Storengy subsequently awarded Costain the contract for engineering, procurement and construction management (EPCm) of the brine and water facilities, which have been recently completed safely, on time and on budget.

The brine and water infrastructure contract included the creation of 10 wellheads, 26km of buried pipelines, a pumping station capable of delivering 45,000m3 per day, an electrical substation and control systems.

Costain has also successfully completed another Storengy contract for the FEED of the associated Stublach gas plant.

Some 2km away, Costain is also involved in a gas storage project at Holford for Holford Gas Storage, part of German energy utility E.ON. Under this contract, eight  caverns will be created, capable of retaining up to 156 million m³ of gas. This is equivalent to supplying 3.5 million homes for 10 days.

Each cavern will be 100 metres in diameter and 100 metres deep - tall enough to hold Big Ben.

Costain's responsibilities include the engineering, procurement and construction management contract to complete the gas plant infrastructure and wellhead modifications.

As always, the projects have had their own particular hurdles to overcome, explains Charles Sweeney, Managing Director of Costain Energy and Process. One of these has been their locations, close to several working farms and residential villages.

Stublach "is being installed in the heart of the Cheshire countryside, so developing the design so that it would be acceptable and get through the planning process was a challenge. Then we had to execute it within the strict rules and regulations that were set against the plant's construction."

Other environmental aspects of the sites included the relocation of great crested newts, bats and birds and drainage issues.

"Site drainage was a significant issue because the local area is highly susceptible to flooding, so early drainage work was necessary," says John Meakin, Project Manager at Holford.

With only one brook available to dispose of excess water from the site, Costain installed an underground 'storm cell', to gather excess water and dispose of it into the brook gradually.

At Stublach, meanwhile, the rural nature of the site meant constraints on deliveries of materials, says Project Manager David Richardson: "We could only bring in 30 HGVs a day." Close liaison with the Environment Agency was also required to build crossings over several drainage ditches and streams, as well as laying pipework under them.

Both sites picked up several plaudits for safety including RoSPA Gold Awards and, in Stublach's case, a safety award from the Society of British Gas Industries.

Costain's work will bring security of supply to UK energy users for years into the future and is a further example of the Group helping improve the nation's infrastructure.