Costain news

ICE Award For Costain

22 April 2010

The Thames Water Ring Main Extension Project has received a special award from the Institution of Civil Engineers for its work helping to ensure the future resilience of London's water supply.

The project has seen several major contractors, including Costain, driving nearly 10km of new tunnels plus four large-diameter pump-out shafts through some of the capital's most congested areas - both above and below ground.

The aim was to increase the Ring Main's capacity by 500 million litres per day, without adversely affecting further extensions in the future. This was to be achieved without any road closures, transport suspensions or interruption to amenities.

The Costain team based at the Hampton Advanced Water Treatment Works in southwest London was responsible for sinking one of the major shafts and tunnelled connections to an existing Ring Main shaft and the High Lift Pumping Station.  The shaft was 15m in diameter and 40 metres deep. The connecting tunnels were constructed either by open-face heading or using a Costain Tunnel Boring Machine.

Ground conditions were an initial problem, with an unexpected substantial brick Victorian pumping station three metres below the surface whose foundations extended a further six metres down. The team also had to contend with contaminated ground and the diversion of multiple utilities.

The shaft was constructed using traditional underpinning methods through the historically disturbed ground, followed by an innovative design employing a sprayed concrete lining (SCL) for the remaining two-thirds. The SCL was a value engineering/contractor proposal comprising two layers of sprayed concrete which sandwiched a spray applied water-proofing membrane.

This alternative method provided benefits in cost and programme where the tunnel portal construction was considerably simplified.

ICE judge Chris Wise, speaking at the 2010 London ICE Awards where the special prize was presented to the teams involved in the 10km extension project, commented: "At 80km long, the Ring Main's achievements were already breathtaking and fundamentally underpin life in this city as we know it.

"With these four new extension projects the water supply will be even better, giving greater certainty, greater resilience, using less energy and extending both its usefulness and its sustainability."