New School Projects Announced

8 April 2010

The Costain team handling the renewal of education facilities in the London borough of Lewisham is gearing up for a busy year after the local education authority issued the go-ahead for a cluster of new school projects.

Learning21, a joint venture between Costain and VT Group, was awarded the Lewisham Building Schools for the Future (BSF) Project in 2007.  BSF is a government programme to renew all of the country's secondary school estate, and at Lewisham, Costain and VT have formed a Local Education Partnership (LEP) with the London Borough of Lewisham and Building Schools for the Future Investments.

Costain has already completed the first two schools in the Lewisham BSF. These are now fully in use and delivering education in a first class state-of-the-art environment.

As a part of the ongoing programme, Lewisham has now issued New Project Instructions for no fewer than eight schools. "Effectively this is a letter from the Authority to the LEP asking us to prepare a proposal for the design and construction of the schools," said Jerry Williams, Costain's Education Sector Director.

"The Authority provide their requirements, and an education 'vision', and we develop a design, working with the schools and others, such as the facilities management and the IT providers. The schemes go through a two-stage development process - an initial outline design and cost plan, then the full design and pricing leading to contract award."

The approximate value of the remaining programme of work, which will consist mainly of secondary schools, is £130 million. The projects are a mix of new-build and refurbishment, and are procured either under a Private Finance Initiative, or Design & Build arrangement. The most advanced of these latest new schools, Deptford Green, is also one of the most substantial, with a construction value of approximately £28 million.

"It takes us just over a year from getting the New Project Instructions to getting underway on site," said Jerry. "The projects will be starting on site late 2010 and 2011; the build times vary, but the construction will mainly be 2011-12."