Costain news

All Projects On Time And On Budget

2 June 2010

The recent round of Asset Management Plan (AMP 5) awards from regional water companies has brought further success for Costain in Wales with a new contract from Dŵr Cymru Welsh Water (DCWW).

Having successfully completed the five-year AMP 4 contract worth almost £70million, Water Sector Director North, Phil Appleby, feels justified in saying: "We've got a satisfied customer.

"We've had more than 150 individual projects delivered to time and within target price."

Typical contracts have included a series of improvements to Wastewater Treatment Works (WwTW) and Combined Sewer Overflows (CSOs) to improve the quality of outflows to watercourses and the sea and thus assist DCWW in meeting its regulatory obligations.

A significant element of the programme has been flooding projects, where relief has been provided to properties that have previously suffered internal and external flooding from foul water and sewage. These projects have relieved almost 800 properties from the prospect of future flooding damage.

Another project that required particularly sensitive handling was improving an existing Water Treatment Works (WTW) at Mynydd Llandegai in the Snowdonia National Park. Situated within a Site of Special Scientific Interest, the buildings required extensive cladding in local stone to blend in to the landscape and match existing features.

The new AMP 5 framework contract, which is likely to see Costain undertaking individual projects worth anything from £50,000 to £8million, is likely to have a roughly similar overall value over the next five years, says Phil.

Although work has so far been primarily in North Wales, there is the chance that this will be extended to the south of the Principality, he adds.

John Madden, Framework Director for Costain at DCWW, is particularly proud of the Costain team's Health & Safety record that has maintained an Accident Frequency Rate (AFR) of zero for more than 3.25 years.

John also highlights a £3.5million project to create a new WwTW at Amlwch, on Anglesey, which, driven by legislative deadline, was due to complete on the last day of 2008 but, due to circumstances outside Costain's control, only got underway in March of that year.

What should have been a 15-month project was nevertheless brought in on the original deadline, after what John describes as particularly close working with Costain's supply chain and other DCWW partners.

AMP 5 is likely to be more focused on maintenance projects than its predecessor, he adds. "Most of the big new works are now built; AMP 5 will be very much a maintenance AMP to ensure facilities continue to comply with standards.

"We've commenced design on a project due to start on site in the autumn at Five Fords near Wrexham. This will be an extension to a WwTW, the largest in North Wales, which will involve building a new advanced digestion plant, phosphorous removal and sludge treatment capacity, both to comply with current legislation and to ease the problems of sludge handling in North Wales.

"A feature of this project is the heat and power that the process will generate from the sewage will be utilised to reduce DCWW's electricity demands at Five Fords. The project is due to complete towards the end of 2011 and will be worth around £8million to Costain."

Another 2011 project will involve the creation of a service reservoir for DCWW near Conwy in North Wales.

John sees the retention of the Costain team in North Wales for AMP 5 as vindication by DCWW of its satisfaction with the quality of delivery in AMP 4 by Costain. "We hope and expect to improve our performance for DCWW in AMP 5 and therefore look to prolong our relationship with DCWW into AMP 6 and beyond."