Costain news

Water Boost For Brighton

19 July 2010

4D, the joint venture that combines Costain with United Utilities and MWH, is helping to deliver a £225million environmental improvement scheme to bring cleaner seas to Sussex.

At present the wastewater receives only basic treatment before being released through an outfall pipe 1.8km off the south coast.

Tunnelling underway

By 2012, a combination of 11km of tunnel, three new pumping stations and a wastewater treatment works at Peacehaven, east of Brighton, will see the wastewater fully treated and then dispersed at sea through a new 2.5km pipeline.

Two 2.44-metre diameter tunnel-boring machines (TBMs) - one ceremonially lowered into one of the 16 shafts that are being excavated along the route on 29 June - have just started their work, which will continue 24 hours a day until next January.

"We're looking to achieve between 10 and 40 metres a day in full production," says Craig Reade, Costain's Project Manager (Infrastructure) on the job. "The geology is essentially chalk, with some flint inclusions and possibly some seams, but nothing too challenging." The TBMs will create nine kilometres of tunnels, with pipejacks driving a further two kilometres and a huge barge, Nordic Giant, having already dug the seabed trench into which the new outfall will be placed.

The largest shaft, at Marine Drive on the eastern edge of Brighton, is 46m deep and 17.5m in diameter. When complete, it will house one of the scheme's three pumping stations; the shaft will be divided into 'wet' and 'dry' halves by a central vertical wall. Wastewater will fill the wet half, which will be lifted by pumps in the dry section and travel by gravity towards another pumping station at Portobello, then onwards to the waste water treatment works at Peacehaven, 11km east of the town.

The tunnel will intercept several existing sewers and add their contents to the eastwards flow.

The Marine Drive pumping station will be covered with a distinctive architectural zinc-domed 'landmark structure' with traditional stone walls. The only sign of the shafts will be manhole covers.

Camouflaging the treatment works

How to hide a 39-hectare, 4.5km-perimeter site containing a state-of-the-art wastewater treatment works? Moving 800,000m³ of earth to create a huge hollow into which the plant can be placed, carefully shaping earthworks around it, then covering most of it with a grass roof the size of almost three football pitches, is one way of doing it.

The aim is to retain the views across the South Downs. When complete, the works will be hidden in a large excavation within the re-profiled landscape.

The main complexity of the project is its sheer scale, says Project Manager (Treatment Works) Graham Sugrue. As well as the vast earthworks, the treatment works will use 26,000m³ of concrete, with 39,000m³ employed across the project as a whole.

"This is very much state-of-the-art. It's the biggest plant of its type," he says. The treatment works will include a £6.5million odour control plant and the arriving wastewater will go through a three-stage treatment process.

After having debris, grit and grease removed, primary treatment will remove solid waste in four huge settling tanks. The resulting liquid will then be passed through a deep bed of polystyrene beads in 10 concrete cells. Bacteria will stick to these beads, which will periodically undergo a 'backwash' process to clean them.

The resulting clean water will then be piped out to sea. The solid waste removed during the treatment process forms a sewage sludge. This is treated so it can be safely used as an organic soil conditioner.

Community aspects

There are significant local sensitivities around this scheme, especially bearing in mind the planning process for this scheme begun in 1993, went through two public enquiries and a judicial review before planning permission was finally granted in 2008, says Sugrue.

This has led to a major community relations programme since Costain moved onsite last August. An exhibition centre for the project has been set up and Community Relations Manager James York holds monthly meetings with residents.

Local schools have been visited, with pupils at one, St Margaret's, being asked to suggest names for one of the TBMs. 'Alice' was the winning contender. Alice in Wonderland author Lewis Carroll came up with the idea of Alice going down a rabbit hole after discovering a narrow passage while visiting a relative in Brighton; the TBM is similarly going underground.

The site employs strict noise and access conditions, a roadsweeping vehicle is employed virtually permanently to keep local roads free of mud and dust monitors are placed around the site. Waste generated by the earthworks at Peacehaven must be retained on site.

 

Pictured top right: As tunnel boring machine Alice is prepared for lowering into position, Brighton Project Director Phil Risbridger (left) welcomes Jon Gilbert, Deputy Headmaster of St Margaret's Primary School, Rottingdean, one of whose pupils chose the TBM's name. Julian Smith, Southern Water's Project Manager (centre) was on hand for the ceremony. 

Pictured bottom right: Tunnel boring machine Alice sees daylight for the last time for several months as it is eased into position at the foot of the Ovingdean shaft, ready to begin work.