Improving asset availability and efficiency

The Costain consultants were approached by a client to carry out conceptual design and provide solutions to improve asset availability and efficiency. The solution was also required to ensure that the terminal could cease to use a particular refrigerant and maintain gas production in line with NTS specification.

  • Service 1

Consultancy & advisory
Complex programme delivery

Challenges

Maximise

business returns over remaining operational life

Consolidate operation

transition from dual terminal to single terminal

Increase asset utilisation

Compliance with environmental legislation

 During the define phase Costain provided: 

  • Process technology consolidation
  • FEED (define phase) study and management
  • Estimating and planning
  • Selection of optimum solution to meet client requirements
  • Completion of the define Phase studies to produce an enhanced scope definition prior to project execution
  • Generation of define phase report, a +/- 15% project TIC estimate and indicative programme for the execute phase 

Costain executed the define phase of the project, providing a solution to meet the needs of the client, and won the EPC part of the project as a result.

We worked in partnership with vendors and in close collaboration with the client, in order to deliver the full onsite implementation within a tight shutdown period assigned by the client, to avoid any financial penalties for our client. 

Contact and social

Energy

Laura Hughes, Sector Director - Energy
01628 842444
[email protected]