Client: Sellafield Ltd
Services: Consultancy & advisory, Complex programme delivery
Key Facts: Modular design consisting of 11 in-cell modules
396 major plant items
65 nuclear class vessels
Over 21 kilometres of pipework
The largest nuclear decommissioning project in the UK at the time of construction, Evaporator D allowed continued reduction in the volume of highly active legacy waste.
Key benefits:
- 7 Consecutive RoSPA Gold Awards for Occupational Health and Safety
- Modular design reduced schedule risk and construction works on restricted site
- Pre-Construction Safety Case developed and accepted in less than 100 days
- 90% of onsite project team recruited in West Cumbria
- 33% of project spend with local SMEs
Additional waste processing capacity
As part of the Nuclear Decommissioning Authority’s strategy, Evaporator D was designed to expand Sellafield’s ability to process nuclear waste material and ultimately reduce inventories at the site.
We worked with Sellafield Ltd to design and construct the new evaporator which was required to evaporate highly active raffinate produced during reprocessing of spent nuclear fuel rods. Once concentrated through evaporation, the highly active liquor produced is subsequently vitrified – immobilising the waste in a stable glass form for long term storage and eventual disposal.
Key Challenges
- Processing of highly radioactive and very corrosive fluids
- Strictly regulated site
- Remote site access
- Located at the heart of an operating nuclear facility
- Congested site - complex design on a restricted footprint
Innovative construction methods
In order to address the challenges outlined above, our experienced team of engineers drew on expertise from within the oil & gas industry to propose a modular design pre-fabricated and tested off-site, a nuclear first at this scale.
The benefits of this modular approach include:
- Reduced schedule risk
- Minimised works adjacent to highly active facilities
- Opportunities for early operator training
- Reduced fault observations at site
- Process plant and equipment proven prior to installation
The modules, the largest of which is 27m in height, were delivered by sea, the first time in the history of the Sellafield site that this method has been used. Major temporary works were undertaken to construct a beach landing area, a bridge across the River Ehen and to widen the railway crossing to provide a delivery route onto the Sellafield site.
"This first ever delivery of a major component to the beach is the culmination of lots of hard work by a great team of people. We are all very proud of our accomplishment."
Tom McClain Sellafield Ltd Project Manager, speaking following the delivery of the first module.
Contact
Bob Anstey
Sector director
[email protected]
Laura Hughes
Sector director
[email protected]